US NRC Blog Update: Taking a Long-Term View on New Reactor Licenses


Taking a Long-Term View on New Reactor Licenses

Scott Burnell
Public Affairs Officer
Since 2012, the NRC has licensed 11 new reactors in the United States. The first four of those are under construction, two in Georgia and two in South Carolina.
The other seven? Their licenses are ready to go whenever the companies involved choose to start building them, and here’s why.
These new reactors are authorized through the NRC’s Combined License process. Under this approach the license includes permission to both build a reactor and operate it later, as long as a detailed list of completion requirements are met.
A Combined License includes the same 40-year operating period as the licenses for today’s reactors. Those 40 years start when the NRC concludes the reactor has been built according to its license and can operate safely. The construction portion, on the other hand, is set up without a definitive expiration date.
We base our permission to build the reactor on our review of technical and environmental information the applicant provided. Issuing a license means we found all that information acceptable.
Let’s imagine Company X receives a Combined License and waits 10 years before deciding to start construction. If the original information is still valid, the project could get underway. Most categories of information won’t change in that time. The license includes provisions where the company must account for new information when it decides to start construction.
All of this means that companies with a Combined License can therefore take additional time to consider those issues affecting the business decision to construct or not that fall outside the NRC’s jurisdiction. For example, a state’s utility agencies can create or revise policies on how the state obtains and pays for electricity. Changes in interest rates, prices for other electricity sources and even the makeup of regional electricity markets can affect the company’s overall business case.
Once a company concludes conditions are right for using a Combined License, the utility will give the NRC advance notice of its intent to start construction. The NRC will inspect construction activities and otherwise ensure the company meets relevant requirements for protecting the public.